What type of work is categorized as 'new work' in a construction contract?

Prepare for the NICET Level 1 Highway Construction Test. Study with flashcards and multiple choice questions, every question includes hints and explanations. Ace your exam seamlessly!

In the context of a construction contract, 'new work' refers to tasks or activities that were not originally included in the contract or scope of work but must be performed to complete the project. This is often due to unforeseen circumstances that arise during the construction process, requiring adjustments or additions beyond what was initially planned.

The identification of 'new work' as unforeseen work or quantity adjustments is essential in understanding how construction contracts adapt to changing conditions. It encompasses situations where tasks must be completed that were not anticipated at the project’s outset, highlighting the dynamic nature of construction projects. By defining 'new work' in this way, contracts allow for flexibility in management and resource allocation to ensure project goals are met despite unexpected challenges.

In contrast, the other options describe situations that do not fall under the definition of 'new work.' Work that is referred back to original designs may involve reverting to previously established parameters, rather than generating new tasks. Changes requested by the contractor could relate to modifications within the existing scope rather than introducing entirely new work. Finally, additional tasks defined in prior notices could be considered as part of contract changes rather than new work, as they are already acknowledged and planned within the project framework. Thus, option C accurately encapsulates the essence of 'new work

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy